The Ministry of Labour has lifted two Stop Work Orders that were issued for the 8th Street East Reconstruction site. The Stop Work Orders were issued to the contractor as a result of the slope failure on the 8th Street East hill that occurred on May 19, 2015. Both stop work orders were removed without conditions on June 11, 2015 following an on-site inspection by a Ministry of Labour inspector to review the temporary repairs of the slope undertaken by the contractor under the direction of a Professional Engineer.